Crossrail Balfour Beatty (MDA)

OLE Switch Installation – Sep 2016 – July 2017

Circa £1.5M

2 Switch installation teams including management responsible for aspects from planning through to installation of 102 switches across the route. This being a combination of switch types: Track Section Switches, Circuit Main Earth & Power Supply Switches, Motorised and Manual operated . 

In addition supplied our internal resources to support the wiring and registration activities to meet key milestones on the project. Engineers, Construction Managers, Senior Supervision, OLEC Competent staff. 