Amended Policies, Procedures & Other Documents Briefing – MODEL SAFETY RULES (PP091)
The following Policies/Procedures/associated forms are detailed within this briefing:
- Model Safety Rules (PP091)
- LV Permit (PF077.0)
- HV Permit (PF077.1)
Line Managers shall make their team aware that this procedure and its associated forms have been included into the ECS Integrated Management System.
No changes made to the existing ECS Power process, this procedure has been included into the ECS Integrated Management System.
The purpose of this procedure is to detail the requirements and arrangements that ECS Power apply to safely work on HV/LV electrical distribution equipment and to ensure that these arrangements are carried out correctly.
This procedure applies to all ECS Power personnel and its contractors that are involved in working on electrical equipment.
The procedure provides a common framework and allows best practicable safety standards and is detailed as followed:
- General Provisions
- Definitions
- General Safety Precautions
- Safety Precautions For Work on or Near High Voltage Systems
- Procedures For Work On Particular Items of Plant, Apparatus or Conductors
- Safety Precautions For The Testing of High Voltage Apparatus
- Safety Precautions & Procedures For Work on Low Voltage Systems
- Responsibilities of Persons
- Permit to Work Systems